Skip to content
CurriculumLesson 13 · CPU Scheduling
Intermediate~14 min

Priority Scheduling

Priority scheduling encodes importance. The highest-priority ready process runs next — and low-priority processes may never run unless you add aging.

In plain English

Priority scheduling is a VIP line. The most important job goes first.

By the end you will be able to

  • Trace non-preemptive priority scheduling.
  • Decide which priority number means higher priority.
  • Explain starvation and aging.
  • Compare priority scheduling with SJF.
01

The algorithm

Each process has a priority. At every decision point, choose the highest-priority process among those that have arrived. In non-preemptive priority, run it to completion. In preemptive priority, a newly arrived higher-priority process can interrupt the running one. Be explicit about direction: many systems treat a lower number as higher priority, but the convention is not universal.

lesson-13.osOS
time = 0;
while unfinished:
    ready = arrived unfinished processes
    if ready empty: time = next arrival; continue
    p = ready with highest priority
    run p to completion
    p.completion = time
02

Worked example

Processes: P1 arrival 0 burst 5 priority 3, P2 arrival 0 burst 3 priority 1, P3 arrival 0 burst 8 priority 2. Lower number = higher priority. P2 runs 0–3, P3 runs 3–11, P1 runs 11–16. Completion: P2 3, P3 11, P1 16. Waiting: P2 0, P3 8, P1 11. Average waiting = 6.33. If P2 keeps arriving, P1 can starve.

lesson-13.osOS
| P2 | P3       | P1    |
0    3          11      16
03

Starvation and aging

A low-priority process can wait indefinitely if higher-priority work keeps arriving. Aging gradually increases the priority of waiting processes, so even a low-priority job eventually becomes competitive. Another option is to reserve a share of CPU time for each priority class. Priority scheduling is useful when importance is real, but it needs a starvation policy.

Watch it happen

Step through the worked example. Play it, pause it, or move one step at a time.

step-by-step

Step 1 of 3

t = 0 → 3 · P2

At t=0, P2 has the highest priority among ready processes, so it runs until t=3.

Gantt chartPriority
P2
P3
P1
016
PIDArrBurstRemStateDone
P1055ready—
P2030done3
P3088ready—
ready at t=3:P1P3

Key takeaways

  • Priority scheduling chooses the highest-priority ready process.
  • Lower number often means higher priority, but check the convention.
  • Non-preemptive priority runs the chosen process to completion.
  • Low-priority processes can starve.
  • Aging raises priority over time to prevent starvation.

Common pitfalls

  • Mixing up which priority number is higher.
  • Running a process that has not arrived.
  • Forgetting that preemptive priority can interrupt a running process.

Kernel notes

  • State the priority direction before solving.
  • Trace the ready set at each decision point.
  • Explain aging with a concrete low-priority process.

Quick check

0 / 2 answered

1. In a system where lower numbers mean higher priority, which process runs first?

2. What problem does aging solve?